Investment Technology Group

Boston, MA

DH Project Management's Scope

Project Date: 3rdQuarter 2008

Square Footage: 60,000

Product Type: Finance

Project Type: OPM, Relocation Management

Headcount: 125

Project Duration: 9 Months

Summary:

DH was hired in the fall of 2008 as the overall project manager for a complicated two-phase project consisting of the following:

Owner’s Project Management

Phase I

  • Coordinated the installation of a stand-by emergency generator:
  • This location is a BCP site for ITG, a 600KW emergency generator was required to be designed and installed to support trading as well as serve as a BCP site for other locations
  • Data Center: The data center supporting the trading floor and software development is approximately 2,500 square feet and was designed to serve ITG through the full term of their lease
  • Trading Floor: An approximately 50 seat area with room for expansion
  • The entire trading floor is connected to the emergency generator to insure business continuity in the event of an emergency
  • Support offices: One floor of support offices consisting of food services, conferencing, IT, marketing, and design & development.

Phase II

  • Offices: One additional floor (25,000 square feet) of support offices.
  • Subtenant space: 11,000 square feet was built and furnished to suit the needs of ITG’s current subtenant as well as ITG’s future needs.